HUBBLE SPACE TELESCOPE DAILY REPORT #1172 PERIOD COVERED: 0700 EST Daily Status Report as of 182/1200Z. 1.0 ACTIVITIES SCHEDULED AND ACCOMPLISHED: 1.1 Completed Two Sets of WF/PC-2 5369 (HST Medium Deep Survey: Cycle 4 Medium, High Galactic Latitude) The WF/PC-2 made a series of observations of high latitude objects as part of a medium deep sky survey. The observations were taken in parallel with other prime science observations. The science observations were executed as scheduled, and no anomalies were noted. 1.2 Completed WF/PC-2 5570 (WF/PC-2 Cycle 4 Calibration: Earthflats, Large set) The WF/PC-2 was used to make a set of Earth flat calibration images using different filters in order to construct high quality flat fields of the OTA illumination pattern. The science observations were executed as scheduled, and no anomalies were noted. 1.3 Completed WF/PC-2 5427 (Calibration of Nearby Galaxy Type IA Supernovae as Standard Candles) The WF/PC-2 was used to make observations of nearby galaxy NGC-4496-A-F as part of an effort to find Cepheids in this galaxy which have produced Type I supernovae. The observations were executed as scheduled, and no anomalies were noted. 1.4 Completed WF/PC-2 5415 (The Distance to the M-96 Galaxy Group: Cycle 4 Medium) The WF/PC-2 was used to make observations of Cepheid variable stars within the galaxy NGC-3368 which itself is located in the M-96 galaxy cluster. This is to help determine the distance to this galactic group, and to improve the determination of the Hubble constant. The observations were executed as scheduled, and no anomalies were noted. 1.5 Completed WF/PC-2 5378 (Morphological Evolution of the Galaxies in Clusters at Z=0.5) The WF/PC-2 was used to make observations of galaxy GAL-CLUS-1 to study its morphology. The science observations were executed as scheduled, and no anomalies were noted. 2.0 FLIGHT OPERATIONS SUMMARY: 2.1 Guide Star Acquisitions: Scheduled Acquisitions : 3 Successful : 3 Acquisition failed to course track at 182/0818Z. Subsequent acquisitions were successful. Scheduled Reacquisitions : 13 Successful : 13 2.2 FHST Updates: Scheduled :7 Successful :7 2.3 Significant HSTARs: None 2.4 Operations Notes: All HST subsystems are performing nominally as operational personnel approach the long holiday weekend. 3.0 ANOMALY STATUS: 3.1 Significant New Anomalies: None 3.2 Significant Unresolved Anomalies: None 4.0 SIGNIFICANT FORTHCOMING EVENTS: Nothing at this time.