HUBBLE SPACE TELESCOPE DAILY REPORT #1994 PERIOD COVERED: 0000Z (UTC) 10/29/97 - 0000Z (UTC) 10/30/97 Daily Status Report as of 303/0000Z 1.0 ACTIVITIES SCHEDULED AND ACCOMPLISHED: 1.1 Completed Seven Sets of STIS/CC 7782 (STIS Non-Scripted Parallel Archive Proposal - Half Orbit) The Space Telescope Imaging Spectrograph (CCD) was used for a non-scripted parallel archive proposal (one-half orbit). The observations were executed as scheduled, and no anomalies were noted. 1.2 Completed STIS/CCD 7802 (Daily Darks to Update Acquisition Bad Pixel Table) The Space Telescope Imaging Spectrograph (CCD) was used to make calibration observations to obtain daily darks to update the acquisition bad pixel table. These daily darks are intended to identify hot pixels for update to the acquisition on-board FSW hot pixel table. Daily hot pixel lists can also be used for science data analysis. The observations were executed as scheduled, and no anomalies were noted. 1.3 Completed Three Sets of WF/PC-2 7621 (WF/PC-2 Cycle 7 Supplemental Darks PT1/3) The WF/PC-2 was used to make supplemental dark calibration images. This set of calibrations is intended to obtain three dark frames every day to provide data for monitoring and characterizing the evolution of hot pixels. The observations were executed as scheduled, and no anomalies were noted. 1.4 Completed STIS/CCD 7711 (STIS CCD G750L Fringing Flats.) The Space Telescope Imaging Spectrograph (CCD) was used to investigate and monitor the STIS CCD flat-field fringing in the G750L grating at it's nominal wavelength setting {7751A}. WAVECALs were also taken at the same gain and wavelength setting. Typical S/N = 100 for each integration, and gain = 4 on each. The observations were executed as scheduled, and no anomalies were noted. 1.5 Completed NIC/2 7418 (Imaging of Younf Stellar Object Circumstellar Nebulosity) WF/PC-2 observations have shown that several young stellar objects in the nearby Taurus molecular clouds are seen only indirectly via scattered light. New NICMOS (Camera Two) images of HARO6-5B will be compared with the existing WFPC2 images and with model reflection nebulae to constrain the circumstellar density distributions. The dark absorption lanes already seen in these systems suggest that the NICMOS images will reveal edge-on disks similar to the HST results for HH 30, and thus allow direct observation of the disk geometry. The observations were completed with no reported anomalies 1.6 Completed WF/PC-2 7625 (WF/PC-2 Cycle 7 Earth Flats) The WF/PC-2 was used to make a series of Earth flat calibration images. These flat fields will allow mapping of the OTA illumination pattern and will be used in conjunction with previous internal and external flats to generate new pipeline superflats. The observations were completed as planned, and no anomalies were reported. 1.7 Completed WF/PC-2 6905 (WF/PC-2 Cycle 6 Calibration: Internal Monitor) The WF/PC-2 was used to make several internal calibrations observations including biases and internal flats as part of a Cycle 6 calibration procedure. A variety of internal exposures are run weekly to verify and monitor the health of the camera. The observations were executed as scheduled, and no anomalies were noted. 1.8 Completed NIC/2 7331 (Near-IR Properties of the Bulges of Spiral Galaxies) The Near Infrared Camera (Camera Two) was used to make infrared observations of the bulge in spiral galaxy NGC-7188. Near-IR data at HST resolution are essential for correcting for the effect of dust and will enable us to derive robust nuclear properties for the sample. The observations were executed as scheduled, and no anomalies were noted. 1.9 Completed WF/PC-2 7431 (Snapshot Survey of Microlensed Source Stars) The WF/PC-2 was used to make snapshot survey images of microlensed source star Macho-95-1. Gravitational microlensing surveys have revealed an excess of lensing events over theoretical predictions toward both the Large Magellanic Cloud and the galactic bulge. The observations were completed as planned, and no anomalies were reported. 1.10 Completed NIC/1/2 7243 (High Resolution Imaging of Io) The Near Infrared Camera (Cameras One and Two) was used to make observations of Jupiter's moon Io. The technique of super-resolution imaging will be used to obtain near-IR images of Io with sufficient resolution to map the surface on this volcanically active satellite of Jupiter. Observations were also made of standard star HD201592. The observations were executed as scheduled, and no anomalies were noted. 1.11 Completed Two Sets of WF/PC-2 7786 (Pure Parallel Archive Survey - Continuation) The WF/PC-2 was used to make observations as part of an archival survey program in which the images were taken in parallel with the prime science observations. These WF/PC-2 parallel observations were obtained in the ultraviolet in a search for interesting objects. The observations were completed as planned, and no problems were reported. 1.12 Completed Two Sets of FGS 7680 (FGS3 and FGS1R TRANS Mode Plate Scale Calibration) The Fine Guidance Sensors were used to make astrometric observations of the binary star UV-Ceti in order to perform a FGS #3 and FGS #1R TRANS mode plate scale calibration. Several GO programs have revealed an effect where the measured separation of the components of a binary system is sensitive to its orientation relative to the FGS interferometer axis, i.e. HST roll. The calibration observations were completed as planned, and no problems were reported. 1.13 Completed WF/PC-2 6868 (Super Flat Galactic Disks) The WF/PC-2 was used to make observations of the super flat disk on late-type galaxy UGC-711 which is located in our local super cluster. These data will be suitable for studies of the structures of the disks as well as properties of disk components, such as dark nebulae and star clusters. The observations were completed as planned, and no anomalies were reported. 1.14 Completed NIC/1/2/3 7726 (NICMOS One Orbit Parallel) The Near Infrared Camera (Cameras One, Two and Three) was used to make a one orbit parallel calibration observations. The observations were executed as scheduled, and no anomalies were noted. 1.15 Completed Two Sets of STIS/CCD 7783 (STIS Parallel Science) The Space Telescope Imaging Spectrograph (CCD) was used to make observations taken in parallel with the prime science. The observations were completed, and no problems were reported. 1.16 Completed NIC/1/2/3 7729 (NICMOS Short One Orbit Parallel) The Near Infrared Camera (Cameras One, Two, and Three) was used to obtain "JHK" imaging of sky regions while another instrument was prime. These observations were part of the short NICMOS one-orbit parallel program. The observations were executed as scheduled, and no anomalies were noted. 1.17 Completed NIC/2 7420 (A Near-Infrared Search for Very Low Mass Companions to Stars Within 10 Parsecs of the Sun) The Near Infrared Camera (Camera Two) was used to make searching observations for very low mass companions to variable star LHS3799. This star is known to be within 10 parsecs of the Sun. The observations were executed as scheduled, and no anomalies were noted. 1.18 Completed Two Sets of WF/PC-2/NIC/3 7382 (The Star-Formation History of the Large Magellanic Cloud) The WF/PC-2 and the Near Infrared Camera (Camera Three) were used to make observations of the disk of the Large Magellanic Cloud. These data will enable us to quantitativly study the intermediate to low-mass stellar populations and the star-formation history of the LMC. The observations were executed as scheduled, and no anomalies were noted. 1.19 Completed STIS/CCD/MA1/MA2/NIC/3 7633 (HDF-South Test Observations) The Space Telescope Imaging Spectrograph (MA1 and MA2) and The Near Infrared Camera (Camera Three) were used to make observations designed to test the FGSs and the potential guide stars which may be acquired during the October 1998 CVZ passage for the HDF-South. Observations were made of star HDFS-22333. A wave length calibration image was also taken. The observations were completed as planned, and no anomalies were reported. 2.0 FLIGHT OPERATIONS SUMMARY: 2.1 Guide Star Acquisitions: Scheduled Acquisitions : 11 Successful : 11 Scheduled Reacquisitions : 5 Successful : 5 2.2 FHST Updates: Scheduled : 17 Successful : 17 2.3 Operations Notes: The SSR interrupt log was dumped at 302/2136Z. 3.0 SIGNIFICANT FORTHCOMING EVENTS: Continuation of normal science observations and calibrations. /DMH