This section describes the current status of ACS calibrations,
as well as plans for Cycle 15.
At the time of writing, the analysis of
SMOV (Servicing Mission Orbital Verification) and Cycles 11
and 12 have been completed, with Cycle 13 largely completed
and Cycle 14 observations largely in hand.
Calibrations of fundamental items such as geometrical
distortions and absolute sensitivity of prime modes are
well in hand. Details and results for low use modes are
being actively pursued.
With the July 2006 switch to Side 2 electronics
and the lowering of the Wide Field Camera
temperature setpoint from -77 to -81 C we have
started a special assessment of calibrations
involving both a small number of new observations
(usually existing monitoring programs exercised
after the switch) and concerted analyses.
More information on this may be found in the
Cycle 15 Calibration section below.
Table of Contents
1: Ground Testing and Calibration
Ground calibration and testing was a prime responsibility of the ACS Investigation Definition Team (Principal Investigator Holland Ford, JHU) and was carried
out at Ball Aerospace in Colorado. Thermal vacuum (and supplemental dry-nitrogen environment) testing in which orbital conditions were simulated was
conducted pre-launch at Goddard Space Flight Center. Filter transmission curves, and detector quantum efficiency curves, were derived at GSFC and JHU. These
tests characterized the basic properties of the optics, the detectors, and the mechanisms. During ground calibration the highest priority was given to those
measurements essential to establish that instrument design specs were being met, and to those measurements that could not be obtained on-orbit. Most of the
non-unique ground test data were superseded by on-orbit measurements as part of the STScI Cycle 11 calibration plan. Successive cycles of the calibration
program both maintain routine calibrations (such as providing darks and biases and tracking evolving CTE) and also brings maturity to determinations of the
overall QE and low-frequency flat fields.
2: SMOV Testing and Calibration
The primary goal of the SMOV3B was a timely commissioning of the HST observatory for normal science operations. For ACS this has included basic testing of
the instrument functionality as well as testing/setting of the focus (internal and external), measuring the sensitivity in all filters, establishing the
geometric distortion and plate scale, quantifying the point spread function for each camera, and adjusting flat fields to properly capture low-frequency
variations for which ground calibrations are always difficult. Data from SMOV proposals are non proprietary and fully accessible through the HST archive. We
list below the program IDs and proposal titles. Details of the Phase II programs may be found via: http://presto.stsci.edu/public/propinfo.html. Some
programs are of very limited technical interest (e.g., Science data buffer check--9003), while others (e.g., WFC flat field stability--9018) collected large
amounts of data in standard filters on objects of potential archival science interest.
Table 1: ACS SMOV Proposals
|
Proposal ID
|
Titles
|
| 8947 |
CCD Daily Monitoring |
| 8948 |
CCD CTE Test |
| 8992 |
ACS ERO Program |
| 9002 |
ACS Dump Test & Verification of Memory Loads |
| 9003 |
ACS Science Data Buffer Check |
| 9004 |
ACS Calibration Lamp Checkout Contingency |
| 9005 |
CCD Functional |
| 9006 |
CCD Temperature Set Point Determination |
| 9008 |
ACS MAMA Initial Turnon & Anomalous Recovery Procedure |
| 9009 |
ACS MAMA Fold Analysis |
| 9010 |
SMOV Contamination Plan |
| 9011 |
ACS to FGS Fine Alignment |
| 9012 |
HRC Coronagraphic Acquisition |
| 9013 |
ACS Coarse Corrector Alignment |
| 9014 |
ACS Fine Corrector Alignment |
| 9015 |
ACS Image Quality Verification |
| 9016 |
HRC Coronagraph Repeatability |
| 9017 |
ACS Image Stability Verification |
| 9018 |
WFC Flat Field Stability |
| 9019 |
HRC Flat Field Stability |
| 9020 |
Preliminary ACS Sensitivity |
| 9022 |
SBC Dark Current Measurement |
| 9023 |
ACS SBC Image Quality Verification |
| 9024 |
SBC Flat Field uniformity |
| 9025 |
Scattered Light in Coronagraphic Obs |
| 9026 |
ACS Ramp Filter Test |
| 9027 |
ACS SBC Geometric Distortion Calibration |
| 9028 |
CCD Geometric Distortion |
| 9029 |
ACS Grism/Prism Performance Check |
| 9031 |
ACS CCD hot pixel annealing |
| 9032 |
ACS CCD Flash calibration |
| 9574 |
Focus Monitor |
3: Cycle 11 Calibration
The SMOV calibration and testing period extended for roughly two months taking routine monitoring of ACS performance through April 2002. With the nominal
start of Cycle 11 at July 1, 2002 and with a desire not to define the final calibration program for Cycle 11 until some flight experience from SMOV could be
obtained, a decision was made to break the Cycle 11 calibration into two parts: (1) an interim program continuing routine monitoring (darks, biases) and
extending characterization in areas not well covered by SMOV, and (2) the standard full program expected to start in July 2002 and run for one year. Tables
13.2 and 13.3 list program IDs and titles for the interim and standard Cycle 11 calibrations
respectively.
3.1: Calibration Priorities
As for any instrument the ACS calibration plan represents a compromise between the desire to calibrate the instrument as well as possible and the
availability of finite resources both in terms of primary HST orbits and in terms of human resources at STScI. The list of priorities that guided the Cycle
11 calibration planning was:
1. Monitor the Health and Safety of the Instrument. This includes obtaining all data necessary to verify that the instrument is performing as
planned and to insure a useful lifetime as extended as possible.
2. Update and Maintain Pipeline Reference Files. Dark, biases, flat fields and sensitivities used in the pipeline calibration need to be accurate
and current. Information on newly released reference files is announced via the Space Telescope Analysis Newsletter and posted on the ACS web page. The
updated list of recommended reference files to be used with each data set is available through the HST Archive, and will be automatically applied when
calibrated data are requested from the Archive.
3. Characterization of Optical Performance. The point spread function and its variation across the field of view needs to be carefully determined
as a function of wavelength.
4. Characterization of detectors. This includes charge transfer effects, long wavelength fringing, hot pixel growth, etc.
Table 2: Cycle 11 ACS Interim Calibrations
|
Proposal ID
|
Proposal Title
|
| 9558 |
CCD Monitor |
| 9559 |
Focus Monitor |
| 9560 |
CCD Linearity Check |
| 9561 |
Internal CTE Monitor |
| 9562 |
Internal Flat Field Stability |
| 9563 |
Photometric Stability |
| 9564 |
UV Earth Flats |
| 9565 |
Contamination Monitor |
| 9566 |
CCD Hot Pixel Annealing |
| 9567 |
SBC Dark Current |
| 9568 |
Grism/Prism Calibration |
Table 3: Cycle 11 ACS Standard Calibrations
|
Proposal ID
|
Proposal Title
|
| 9647 |
CCD Daily Monitor Part I |
| 9648 |
External CTE Monitor |
| 9649 |
ACS internal CTE monitor |
| 9650 |
CCD Hot Pixel Annealing |
| 9651 |
ACS CCD Flash Calibration |
| 9652 |
SBC Dark Current |
| 9653 |
ACS MAMA Initial Turn-on and Anomalous Recovery Procedure |
| 9654 |
ACS photometric Stability |
| 9655 |
ACS Post-SMOV UV Contamination Monitor |
| 9656 |
Stability of the ACS CCD: geometry, flat fielding, photometry |
| 9657 |
ACS Internal Flat Field Stability |
| 9658 |
UV Earth Flats |
| 9659 |
Gain Dependence of Biases |
| 9660 |
Earth Bright Limb Calibration |
| 9661 |
ACS Polarization Calibration |
| 9662 |
HRC+WFC Shutter Stability Test |
| 9663 |
Focus Monitoring |
| 9664 |
SDSS Primary Standards |
| 9665 |
Extreme Red Stars |
| 9666 |
Photometric Transformations |
| 9667 |
ACS PSF Characterization |
| 9668 |
ACS Coronagraph Wavelength Dependence |
| 9669 |
ACS Coronagraph stability and vignetting |
| 9670 |
UV and Narrow Band Filter Red Leak Check |
| 9671 |
ACS Ramp Filter Check |
| 9672 |
Grism/Prism Calibration |
| 9673 |
CCD Daily Monitor (9674 & 9675 continue this) |
The Cycle 11 calibration program was intended to most effectively balance the needs of the community for obtaining excellent science results from the
instrument with the limited resources available (e.g., a nominal limit of 10% time available for calibration). Common uses of the instrument were fully
calibrated.
4: Cycle 12 Calibration
The goal of the Cycle 12 calibration plan was to complete the definition of the ACS calibration by refining the measure of a number of important parameters
of the instrument. These included the geometric distortions, L-flats, sky flats, and the quantum efficiency of the two CCD detectors. Monitoring programs
followed hot pixels, the stability of bias and dark reference frames, the photometric calibration stability, and tracking the degradation of photometric
performance due to CTE losses induced by the continued exposure to cosmic radiation.
The Cycle 12 calibration plan started on October 2003 and Table 4 lists the programs.
Table 4: Cycle 12 ACS Standard Calibrations
|
Proposal ID
|
Proposal Title
|
| 10042 |
CCD Daily monitor |
| 10043 |
External CTE Monitor |
| 10044 |
Internal CTE Monitor |
| 10045 |
SBC Dark Current and Recovery |
| 10046 |
CCD Hot Pixel Annealing |
| 10047 |
UV Contamination Monitor |
| 10048 |
Stability of Photometry, Geometrical Distortions and Flat Fields |
| 10049 |
Internal Flats |
| 10050 |
UV Earth Flats |
| 10051 |
Bias Reference Files for Sub-arrays |
| 10052 |
CCD Postflash Verification |
| 10054 |
Photometric Zero Points |
| 10055 |
Polarization Calibrations |
| 10056 |
Calibration of Photometry of Extreme Red Sources |
| 10057 |
Ramp Filter Wavelengths and L-Flats |
| 10058 |
Grism/Prism Calibrations |
The CCD daily monitoring program continued to provide dark and bias frames to build the corresponding bi-weekly reference files. Separate programs provided
bias reference files for subarrays, and measured the SBC detector's dark current and stability. The CTE monitoring program characterized the CCDs' CTE losses
as a function of time, field crowding and background levels, and defined recipes to calibrate them. Also, accurate measures and monitoring of available
post-flash background levels were made to allow its use in future cycles in mitigating CTE losses. Annealing of CCD hot pixels continued as during Cycle 11,
and possible contamination to the UV throughput was monitored. The photometric zero points of all cameras will be further refined through observations now
obtained of four spectro-photometric standard stars. The photometric calibration for compact or point sources with very red spectral energy distribution was
checked through observations of extreme red stars. The stability of the photometric calibration, geometrical distortions and flat fielding will also be
measured and monitored through dedicated programs. Polarization calibrations were taken to fully characterize the internal polarization of the instrument.
Data to support accurate wavelength measures and L-flats for the ramp filters were acquired. The plan also included accurate measures of the wavelength
calibration of the grism and the prism.
5: Cycle 13 Calibration
The goal of the Cycle 13 calibration plan is to continue refining the definition of the ACS calibration by measuring a number of important parameters of the
instrument, but with a level of resource commitment in orbits that will be lower for areas exhibiting excellent stability to date. These include the
geometric distortions, L-flats, sky flats, and the quantum efficiency of the two CCD detectors. Monitoring programs followed hot pixels, the stability of
bias and dark reference frames, the photometric calibration stability, and tracking the degradation of photometric performance due to CTE losses induced by
the continued exposure to cosmic radiation. New observations will be aimed at testing the wavelength stability of primary filters and further refining the
measure of their bandpasses, and continuing to build up polarimetric calibration.
The Cycle 13 calibration plan will start on October 2004 and Table 5 lists the currently planned programs.
Table 5: Cycle 13 ACS Standard Calibrations
|
Proposal ID
|
Proposal Title
|
| 10367 |
CCD Daily monitor |
| 10368 |
External CTE Monitor |
| 10369 |
Internal CTE Monitor |
| 10370 |
CCD Hot Pixel Annealing |
| 10371 |
CCD Postflash Verification |
| 10372 |
SBC MAMA Recovery |
| 10373 |
UV Contamination Monitor and SBC Dark Current |
| 10374 |
ACS Photometric Stability |
| 10375 |
Stability of Photometry, Geometrical Distortions and Flat Fields |
| 10376 |
Internal Flats |
| 10377 |
UV Earth Flats |
| 10378 |
Polarization Calibrations |
| 10391 |
Wave., Flux Prisms SBC+HRC |
| 10453 |
Short Annealing Test |
| 10720 |
Monochromatic PSF in the Red |
The CCD daily monitoring program will continue to provide dark and bias frames to build the corresponding bi-weekly reference files. The CTE monitoring
program will continue to characterize the CCDs' CTE losses as a function of time, field crowding and background levels, and define recipes to calibrate them.
Also, rough measures and monitoring of available post-flash background levels were made to allow its use in future cycles in mitigating CTE losses (these
observations do not -- and will not for Cycle 14 -- constitute calibrations sufficient for reducing science data). Annealing of CCD hot pixels will continue
as during Cycles 11 and 12, and possible contamination to the UV throughput will be monitored, although less frequently. Observations will be obtained to
further define zeropoints, and to check filter bandpasses. The photometric calibration for compact or point sources with very red spectral energy
distribution will be provided through observations of extreme red stars. The stability of the photometric calibration, geometrical distortions and flat
fielding will also be measured and monitored through dedicated programs. Polarization calibrations will fully characterize the internal polarization of the
instrument.
6: Cycle 14 Calibration
The goal of the Cycle 14 calibration program is to optimally support
science results from the community while balancing the program with available
resources (HST orbits and staff analysis time). Routine calibrations such as darks
are being carried forward at the proper cadence. Also, resources are being
allocated for further characterization of capabilities and calibration of science
observations as required in response to evolution of either performance or
needs reflected in the science program as a whole.
The Cycle 14 program included special observations
to improve ramp, grism and prism calibrations.
The fundamental geometric distortion calibration
for the SBC is being derived, and the sensitivity
of QE and CTE to detector operating temperature
was assessed.
At the time of writing (July 2006) programs
10736, 10737, and 10738 were slightly modified
to obtain calibration data after the switch
to Side 2 electronics and lowering of the WFC
temperature setpoint. The following programs
were added for lower level testing:
11005 Functional Test -- MEB2 Switch
11006 SBC Filter Wheel Checkout
11007 ACS Side 2 Dump Test and Verification
of ACS Memory Load
11008 ACS CCD Side-2 Temp Setpoint
11009 ACS Science Data Buffer Checks
ACS Cycle 14 Cal Plan(PDF)
Table 6: Cycle 14 ACS Standard Calibrations
|
Proposal ID
|
Proposal Title
|
| 10722 |
Geometric Distortion for SBC |
| 10729 |
CCD Daily Monitor |
| 10730 |
External CTE Monitor |
| 10731 |
UV, Narrowband Red Leak |
| 10732 |
Internal CTE Monitor |
| 10733 |
CCD Hot Pixel Annealing |
| 10734 |
CCD Postflash Verification |
| 10735 |
SBC MAMA Recovery |
| 10736 |
UV Contamination Monitor |
| 10737 |
CCD Stability Monitor |
| 10738 |
Earth Flats |
| 10739 |
Internal Flat Fields |
| 10740 |
Photo-Spectrophot Abs. Cal |
| 10741 |
Continuum L-flats -- Ramps |
| 10742 |
Ramp, Grism Wavelengths |
| 10743 |
Improved Wavelengths SBC Prism |
| 10771 |
CTE and QE with Temperature |
ACS Cycle 14 Phase I descriptions
(PDF)
7: Cycle 15 Calibration
The Cycle 15 calibration plan has been developed
and all Phase II programs submitted by November 2006.
This plan includes calibrations intended to
cover up to the next servicing mission, and
therefore has been submitted with six extra months
to June 2008. Routine calibrations continue to be
performed to support the Cycle 15 science program.
Results from Cycles 11, 12 and 13 have been almost
fully obtained, and most of the Cycle 14
calibration observations are in hand with
analyses underway.
New for Cycle 15 is the recognition that
instrument characteristics may have
changed slightly as a result of the Side 2
electronics switch and lowering the WFC
operating temperature by 4 degrees C in July 2006.
The Cycle 15 plan will provide full
calibration of the ACS in this configuration.
Table 7 provides a listing of the programs
in Cycle 15.
Table 7: Cycle 15 ACS Standard Calibrations
|
Proposal Title
|
Notes
|
| 11041 |
CCD Daily Monitor |
| 11044 |
External CTE Monitor |
| 11045 |
Internal CTE Monitor |
| 11046 |
CCD Hot Pixel Annealing |
| 11050 |
UV Contamination Monitor |
| 11051 |
CCD Stability Monitor |
| 11052 |
Internal Flat Fields |
| 11053 |
Earth Flats |
| 11047 |
CCD Post-Flash Verification |
| 11054 |
Photo- Spectrophot Abs. Cal |
| 11048 |
SBC MAMA Recovery |
| 11055 |
Color Dependent SBC flats |
| 11049 |
SBC Darks (with NICMOS) |
| 11056 |
Improved Sensitivity SBC Prisms |
| 11073 |
Checkout of ACS Three-detector Operations |
| 11074 |
Short SBC Darks |
ACS Cycle 15 Phase I descriptions
(PDF)
8: Cycle 16 Calibration
The Cycle 16 calibration plan will be developed after
selection of GO observations, and submission of Phase II
programs. Cycle 16 calibrations will continue to be
performed to support the science program. The timing
of the anticipated Servicing Mission 4 may influence
these calibration plans.
In special circumstances proposers may wish to request additional orbits for the
purpose of calibration. These can be proposed in two ways and should be for
calibrations that are not likely to be in the core calibration programs. An example
of a non-core calibration would be one that needs to reach precision
levels well in excess of those outlined in Table 3.2 in
Chapter 3 of the ACS Cycle 16 Instrument Handbook.
The first type of special calibration would simply request additional orbits within a
GO program for the purpose of calibrating the science data to be
obtained (see Section 4.3 of the Call for Proposals). In this case the extra
calibration would only need to be justified on the basis of the expected
science return of the GO's program.
The second type of special calibration would be performed as a general service to the
community via Calibration Proposals (Sections 3.2.3, 3.4.2 and 3.5.3 of Call for
Proposals). In this case the calibration observations should again be outside the core
responsibilities of the ACS group to perform, and furthermore should
be directed at supporting general enhancement of ACS capabilities with the expectation
of separately negotiated deliverables if time and/or funding are
granted.
Proposers interested in obtaining either type of special calibration should consult
with Instrument Scientists from the ACS Group via questions to the Help
Desk at least 14 days before the proposal deadline in order to ascertain if the
proposed calibrations would be done at STScI in the default program.
Observations obtained for calibration programs will generally be flagged as
non-proprietary.