Status of the NICMOS Cooling System
During Servicing Mission 3B, currently scheduled for February 2002, a closed-
loop cooling system (NICMOS Cooling System, NCS) will be installed to fully
restore NICMOS science capabilities. Currently, the NCS circulator is being
refurbished by Creare, Inc. In June, it is
expected to be returned to Goddard Space Flight Center and integrated into the
NCS.
The detectors under NCS operation will be at around 77 Kelvin, significantly
warmer than the range of temperatures experienced during nominal operations.
The different operating temperature will cause changes in quantities like dark
current, quantum efficiency, and possibly focus position. In order to estimate
NICMOS performance during the NCS era, a suite of programs were executed to
monitor the detector characteristics during the End Of Cryogen (EOC) warmup of
the instrument; the programs were activated Nov. 15th 1998 and continued
throug EOC.
- Program 7961 (pure parallel) took lamp flats four times a day in a number
of filters in all three cameras. The goal was to follow the QE variations
as a function of temperature and wavelength to provide sensitivity
estimates under NCS.
- Program 7962 (pointed) observed a star cluster twice a week in order to
monitor possible focus variations due to varying mechanical stresses in the
dewar.
- Proposals 7963 and 8093 (internal) will took DARKS in all three cameras
once during each orbit which was not affected by the South Atlantic Anomaly
(SAA) or used for one of the other two monitoring proposals. This not only
allowed us to monitor the dark current of the detectors, but also to check
for any temperature-induced electronic effects.
The results of these programs were summarized in
ISR-99-001-REVISION and used to refine the
NICMOS Instrument Handbook V. 4.1 for use in Cycle 11, so that proposers have
the best possible information regarding expected NICMOS performance after the
NCS installation.
|
 |
|