How HST is Scheduled
After an observer submits a Phase II program to STScI, a Program Coordinator
checks the proposal into a database at STScI. If the proposal is
acceptable and if suitable guide stars (if necessary) can be found, the
observations (called visits) in a proposal are assigned scheduling
windows by the Long Range Planning (LRP) group. These windows
range in width from a half day to eight weeks and represent
times that an observation could be conducted on HST. They are subject to
change, but STScI does try to hold to these windows whenever possible.
The actual observations onboard HST are scheduled on week-long
calendars, starting every Monday, 00 Universal Time. Using a pool of observations already
prepared for scheduling by the Program Coordinator Team, the Short Term
Scheduling group begins to construct a given week's calendar three weeks prior to the start of
its execution onboard HST. The actual command loads used to operate
the HST spacecraft and its instruments are generated from these calendars.
Approximately five days before the
start time of a calendar's execution, the command loads to be uplinked to HST are sent
to Goddard Space Flight Center for final checking and verification.
|