Space Telescope Imaging Spectrograph Instrument Handbook for Cycle 22 > Chapter 2: Special Considerationsfor Cycle 22 > 2.5 Scheduling Efficiency and Visit Orbit Limits

2.5
Calendar time for the scheduling and execution of long visits has become severely oversubscribed. To assure a greater degree of scheduling efficiency and avoid such heavy oversubscription, a 5-contiguous-orbit limit was imposed for Cycle 8 and beyond for both CCD and MAMA visits. Observers with programs using more than 5 orbits per target should take note of the following advice when splitting their observations into multiple visits:
There exists the potential for some image rotation between visits unless the SAME ORIENT AS <first visits #> special requirement is used. When SAME ORIENT AS is used, the accuracy is a few milliarcseconds.
HST pointing is generally very stable within a visit (~5 milliarcseconds rms). Small inaccuracies (~20 milliarcseconds rms) can occur between visits, due to the way guide star acquisitions are handled at the start of a new visit. Although these offsets cannot be avoided, there are many situations where they are unimportant, or where their impact can be greatly reduced. For example, if the visit makes observations of several different targets by moving the telescope, and if there is no need for exact offsets (few milliarcsecond accuracy) between the different targets, then the visit could simply be split into separate visits with one target per visit. In cases where a target acquisition is performed for slit spectroscopy, one should follow the same sequence for the target acquisition in the second visit as in the first.
Visits can be scheduled close in time by specifying the GROUP WITHIN visit requirement. Timing constraints of this type, however, should be used only if required by the science, since overconstraining visits affects the ability to schedule efficiently.