Event
|
 |
 |
Agenda for the JWST Spring 2009 Calibration Summit
DAY 1 Tuesday, March 31st 2009
8:30-8:40AM Welcome address & Project Perspective - K. Flanagan
8:40-8:45AM Goals of the meeting - M. Robberto
8:45-10:30AM SESSION 1) Detector processing: from ramps to slopes
------------------------------------------------------------------
Topics: detector artifacts and pipeline processes needed to correct them
(description at module level/flow diagram/list of reference files)
8:45-9:30AM NIRCAM
9:30-9:50AM NIRSPEC
9:50-10:10AM MIRI
10:10-10:30AM Discussion
*10:30-10:50AM Coffee break
10:50-12:30PM SESSION 2) Image processing: Imaging and Coronographic Data
---------------------------------------------------------------------------
Topics: overview of current plans for the reduction of imaging and
coronographic data, starting from slope frames (module level/flow
diagram/list of reference files, etc.)
10:50-11:15AM NIRCAM
11:15-11:40AM MIRI
11:40-12:05AM TFI
12:05-12:30PM Discussion
*12:30-02:00PM LUNCH BREAK
Room N420: Calibration & ITAR policy (working lunch, invite only)
02:00-3:40PM SESSION 3) Image processing: Spectroscopic Data
------------------------------------------------------------
Topics: overview of current plans for the reduction of spectroscopic
data starting from slope frames (module level/flow diagram/list of
reference files, etc.)
02:00-02:30PM NIRSPEC
02:30-03:00PM MIRI
03:00-03:40PM Discussion
*03:40-04:00PM Coffee break
04:00-05:00PM SPLINTERS
-----------------------
Free time for splinter meetings. We expect topics for splinter discussions
will emerge during the day. A list of possible topics may include:
a) steps toward planning of on-orbit calibration , minimization of on‐orbit
calibration time, optimization of calibration models
b) reuse of instrument test software within the STScI data pipeline.
c) Simulated data products
d) Visualisation tools
*** 06:30-9:30PM Tapas party at M. Meixner's home.
DAY 2 Wednesday, April 1st 2009
8:30-10:30AM SESSION 4) SCIENCE CALIBRATION
-------------------------------------------
Topics: review of current plans for absolute calibration and special
needs by SI teams.
08:30-09:10AM JWST astrometry (J. Anderson facilitator)
09:10-10:00AM JWST absolute photometry and spectrophotometry
(K. Gordon facilitator, with contributions from G. Rieke and R. Bohlin)
10:00-10:30AM Discussion
*10:30-10:50AM Coffee Break
10:50-12:30PM SESSION 5) FINAL DATA PRODUCTS
--------------------------------------------
Topics: review/envision plans for advanced data products
-Where the pipeline stops. What will be delivered by the SI.
-Availability of data analysis tools.
-Interaction/support from STScI.
10:50-11:05AM NIRCAM
11:05-11:20AM NIRSPEC
11:20-11:35AM MIRI
11:35-11:50AM TFI
11:50-12:30PM Discussion
*12:30-2:00PM LUNCH BREAK
02:00-3:40PM SESSION 3) GROUND TESTS
------------------------------------
Topics: overview of the data (reference files, tables) that will be critically
required for JWST on-orbit calibration and can be taken only/mainly during
ground tests. Status of analysis (if applicable), data validation and delivery
plans.
02:00-02:15PM NIRCAM
02:15-02:30PM NIRSPEC
02:30-02:45PM MIRI
02:45-03:00PM TFI
03:00-03:30PM Discussion
*03:30-03:50PM Coffee break
03:50-05:00PM Programmatic issues and wrap-up
Topics: possible topics for a final discussion include
-STScI support to ground calibration effort
-Contributed software (either across SI and/or STScI)
-Open mic
-Plan for the next summit, suggestions
05:00PM Adjourn
|
 |
 |