Space Telescope Users Committee
Minutes of the November 1998 Meeting
The Space Telescope
Users Committee met in open session on 9-10 November 1998,
in the Board Room of the Space Telescope Science Institute.
Committee members in attendence were: B. Balick, J. Bally,
J. Clarke, R. Fosbury, J. Frogel, L. Kay, P. McCarthy, F. Mirabel, S. Ortolani,
S. Terebey, R. Thompson, F. Walter (Chair), H. Weaver, and B. Woodgate.
R. Schulte-Ladbeck was absent.
Monday 9 Movember
- S. Beckwith, director of the STScI, welcomed the committee.
He provided
an overview of the main tasks to be confronted in the years ahead.
The
HST budget is currently projected to decrease by about 30%
through the year 2010. Much but not all of this decrease will be due to
the end of costs associated with servicing missions.
Future operations must be streamlined and made more cost-efficient.
The STScI has begun a program, Cheap-Ops,
to identify those costs which could be significantly reduced.
This may impact some user support activities.
However, the
director stressed that the HST will remain in the forefront of scientific
progress, and that the STScI would continue to support unique and novel
uses of the HST.
- *
D. Leckrone provided
the HST Project Scientist's Report.
- The expiration of the NICMOS cryogen is imminent.
Most planned observations were
completed by November 14. During cycle 7, 51% of the prime science
orbits were used for NICMOS observations.
- Despite a shorter than expected
life, NICMOS has yielded a rich record of major scientific achievements.
The NICMOS scientific and performance assessment committee, led by
M. Fall, concluded that NICMOS is a scientific success.
- The NICMOS Cooling System (NCS) was tested on STS-95. Preliminary
reports are that the NCS achieved
the desired temperatures and thermal and mechanical stability, but drew
more power than anticipated. The full HOST report will be made on
December 3. There will be a major engineering review of NCS and the Aft
Shroud Cooling System (ASCS) on January 12-13. The Harwit Independent
Science Review (ISR) committee will reconvene on February 24-25. Any
decision to include NCS in the Servicing Mission 3 (SM3) manifest will
be made subsequent to these meetings by NASA Code S.
- The top science concern is the
ACS
(Advanced Camera for Surveys).
While the latest lot (#7) of CCD detectors appears to have achieved
the required
QE and CTE, there are questions about radiation-hardness. In addition,
the thermo-electric coolers have debonded in the WFC subsystem, and there
are higher-than-expected levels of stray light from internal reflections.
NASA is confident that these problems will be solved with build 3 of the
detectors, and that there will be no impact on ACS delivery.
- Work continues on the SM4 instruments. The
Cosmic Origins Spectrograph
(COS) design concept is now baselined.
§
WFC-3
baseline design is now underway. The WFC-3 Scientific
Oversight Committee (SOC), chaired by Bob O'Connell, has met twice.
Both the HST Second Decade
Study committee and the WFC-3 SOC have examined 3 options for
extending the capabilities of the baseline WFC. These include the
IR-stretch, a 0.8-1.9 micron channel, including dual channel
capability using dichroic filters, and a basic
coronographic capability. These options are feasible and
scientifically exciting, but funding sources have yet to be identified.
The estimated cost for the IR-stretch option is about $30 million
(including contingeny and operations).
- J. Campbell discussed the HST project status.
- The recently completed HOST experiment aboard STS-95 tested three
items which may fly on the SM3 mission: the
advanced computer, SSR2 (second solid state recorder), and the
NCS (Nicmos Cooling System). The computer appeared to work as expected.
NCS was able to achieve a stable temperatures 72.9+/-0.1K (the target
was 72K). The temperature regulation is very stable. There are
vibrations as the system cools to 120K, but below that the system
appears mechanically stable. However, the NCS draws 20% more power
than expected, and because of available power concerns, will not
fly unless the power use can be reduced.
- Aside from the loss of gyro #6 (leaving 4 working gyros), there are
no new hardware problems.
- The major concern now is the timing of the SM3 mission (STS-103). It was
originally scheduled for December 1999. Because of delays with
AXAF,
the launch date for STS-103 has slipped until June 8, 2000, and may
slide still further. The slips have
arisen because the STS manifest shows Columbia returning to Palmdale for
a 16 month refurbishment between the AXAF (STS-93) and SM3 missions.
Only Columbia is able to launch AXAF, or to carry the
SM3 payload, because the other 3 shuttles are all equipped with
airlocks for Space Station construction. The longer this delay, the
greater the likelihood of another gyro failure. HST currently has
4 operational gyros, and can operate with 3. If 2 more fail, HST
must enter safemode until the gyros can be replaced. Recently, the mean
time between gyro failures has been about 1 year.
- J. Green reported on the status of the
Cosmic Origins Spectrograph
(COS). COS is scheduled for launch on SM4, 34 months after SM3.
At this early stage, the development is on schedule and no problems
have been identified.
- * K. Long
presented the status of the current scientific instruments.
- WFPC-II
is stable and functioning normally. Bright targets are stable, with
2% peak-to-peak fluctuations over 4 years. Faint target photometry is
affected by the CTE problem and the "long vs. short" effect, but is
correctable to 5% (generally to better than photon noise).
- STIS is
also operating
stably. The only significant problem is the growth of hot CCD pixels.
About 1% of the CCS pixels are hot at the 0.1 e/s level, and about 200
pixels exceed 10 e/s, and cause dark trails and ringing. All supported
STIS modes now have sensitivity calibration. A 25% improvement in
on-target observing efficiency is expected during cycle 8, because
WAVECAL exposures will be undertaken in occultation and local rate check
images will not be saved. In addition, 25% more time will be available
for MAMA observations due to refining of the SAA contours. A number of
other enhancements were reported. With the installation of the ASCS
in SM3, the STIS operating temperature will decrease, and the NUV-MAMA
dark current should drop by a factor of 2-3.
- §
NICMOS performance remains stable as the exhaustion of its cryogen
approaches. The current estimate is that the cryogen will be exhausted
within 10 days of December 1. There are no scheduled NICMOS science
observations after November 14. There have been problems in the NICMOS
data processing. The pipeline does not yet correctly treat the
floating bias
levels, bias jumps, and cosmic ray persistence, so the NICMOS user
must undertake a more
interactive approach to data processing if the goal is to approach the
ultimate instrumental sensitivities.
- The
FGS
performance remains acceptable. FGS1R will be the Astrometer for cycle 8. It's
interferograms are stable at the 1% level (compared to 7% for FGS3).
- §
K. Long also addressed three outstanding Planetary and Moving Target
(MT) issues.
1.) Finder charts have been routinely provided for non-Solar System
targets for at least 2 years, but are still not routinely available for
moving targets. It was indicated that such charts would be available in
time for cycle 8 GOs.
2.) The STScI currently has no explanation
for the large (~50 pixel) image shifts that are sometimes detected
between consecutive STIS images of MTs. Similar shifts have never been
reported for any fixed target programs. The source of the problem has yet
to be identified.
3.) An STScI
analysis indicates that STIS MAMA observations of comets made under
gyro tracking control (which would be needed for comets having
poorly-determined ephemerides) were technically feasible but would
require a significant investment of STScI resources. A decision on
whether to execute such observations would have to be made on a
case-by-case basis after performing a cost versus benefits analysis and
after evaluating the likelihood that the observations could be
successfully executed without endangering the MAMA detectors.
- K. Long described the user support plan for cycle 8.
In sum, it is very
similar to the plan used during cycle 7. Most GOs will notice no changes.
Larger changes are expected later, following the results of the
user survey, and as Cheap-Ops are implemented.
- K. Long also reported the decision to
discontinue routine, systematic
data quality checks. While this process has been time-consuming, it
means that data will now go to users and to the archive without ever
being seen by STScI staff.
- §
K. Long discussed the utilization of the community parallel data. At
present, 20% of the requests for non-proprietary data are for community
parallels. Based on this, the program seens to be a success.
- §
P. Stanley presented the Planning and Scheduling Operations Status
Report. Overall observing efficiency remain high (about 50%), despite the
need to schedule all NICMOS observations prior to November 15.
All Cycle 5 observations have now been completed; cycle 6 is 81% complete
and cycle 7 is 68% complete. Because STIS-MAMA observations can only be
scheduled during the 5-7 SAA-free orbits each day, scheduling the rest of
cycle7 will be difficult, but by increasing the flexibility of the CCD
visits, it is expected that observing efficiency will remain high and that
most of the remaining cycle 6 and 7 observations will be carried out before
the end of cycle 7, 33 weeks from now.
- *R. van der Marel
presented a preview of cycle 8. As of the date of the
STUC meeting, the panels had met, but the TAC had not.
- 1052 proposal were submitted (109 archive, 64 snapshot, 21 TOO, 3 pure
parallel).
- 13,990 GO orbits were requested; 3300 are available
- 5339 SNAP targets were requested; 1000 will be scheduled.
- Instrument demand: 56% STIS; 41% WFPC2; 3% FGS.
- The cycle 8 requests are up 4% over the cycle 6 requests, but
are down 18% (proposals) and 37% (orbits) with respect to cycle 7.
- 88% of the proposals are small (<30 orbits); 10% are medium (30-60 orbits)
- The 16 review panels met 18-30 October (3 days per panel); the TAC
met November 18-19.
- Notifications will be sent no later than December 18.
- §
B. Whitmore summarized the results of the user
survey. 349 current and former users responded to the e-mail
and web-based survey. Three focus groups have been formed. These will
examine the:
- Proposal Processing and Scheduling System. Chair: A. Koratkar
- Calibration, Analysis, and Archival Support. Chair: C. O'Dea
- Software Support for Users. Chair: D. Shaw.
The focus groups will report back by December 15, and a joint report will
be prepared for the director by the end of 1998. This report will be used to
make recommendations on how user support can be modified to save costs in
the future.
- H. Ford discussed the current status of the
ACS. The current lot of CCDs
is the best yet, and preliminary indications are that they will meet
the goals for QE and CTE. In testing, problems were discovered with
internal scattered light and with the thermo-electric coolers
debonding from their substrates. These problems can be fixed when the
new detectors are installed.
- *§
B. Balick and J. Frogel,
representing the WFC-3 SOC, discussed the
state of the instrument, and presented the scientific rationale for the
IR-stretch concept. This would be a large-format 0.8-1.9 micron
wide-field camera, with a discovery space (area X QE)
exceeding that of
NICMOS by a factor of 10-20.
J. MacKenty reviewed the baseline instrument concept, and
discussed the
engineering aspects of the IR-stretch concept. One can reach 1.9 microns
using only thermo-electric cooling.
- R. Brown updated the committee on the status of the Second Decade Study.
- The committee was given a document summarizing the
Y2K compliance activities at the STScI.
- After an executive session, the committee adjourned for the night and
were treated to dinner by S. Beckwith and D. Macchetto.
Tuesday 10 November
The committee reconvened on Tuesday November 25 at 8:45 AM in executive
session. The public session began at 9:00AM.
- R. Fosbury reviewed the activities of the ST-ECF (European
Coordinating Facility) in support of HST users, and described the new
agreement between NASA and ESA to cover the next decade.
ESA has agreed to allocate the funding equivalent of one "flexi-mission"
(about $200 M in FY96), principally in support of NGST activities.
P. Jakobsen has been appointed NGST study scientist for a team which
will, over the next 9 months, monitor and review studies of a 1-5 micron integral-field
spectrograph, a visible light camera/spectrograph, and
appropriate telescope/payload technologies in Europe.
Meanwhile, as part of the new ESA/NASA agreement, the ST-ECF
has begun work on post-operational instrument
calibration and archiving,
GSC-II plate processing, and HST/NGST outreach.
- In response to the article in the November issue of "Physics Today",
F. Walter asked the Institute and the Project to review their
policies on proprietary time. There are no changes planned in the
current policy.
- J. Bally asked for a clarification of
NASA's policy on press releases.
D. Leckrone stressed that the purpose of press releases is not to
"promulgate officially-sanctioned final answers", but to inform the
press and the public about the progress and achievements of the HST.
The primary aim is to "engage the public in the scientific process".
He noted that in a recent (unscientific) CNN poll, 97% of respondents
rated HST favorably.
- A. Fruchter presented an overview of the HDF-S campaign.
The data were made public on November 23.
- L. Petro and A. Koratkar reviewed the plans
for protecting the HST
during the Leonid meteor shower. The HST was pointed away from
the expected radiant of the Leonids for a 10 hour period.
The Director issued a call for ideas, which produced 27 proposals
(3 engineering) to utilize these 10 hours. An advisory panel reviewed
the proposals, and selected one to obtain CCD imaging and slitless
spectroscopy of PKS2200-238. There are parallel WFPC-2 observations, but
no NICMOS data. These data will be non-proprietory.
- Nominations for the new chair were deferred by majority vote. A
nominating committee consisting of F. Walter, B. Balick,
J. Frogel, and P. McCarthy presented a slate of nominees, chosen both
from within and without the committee, to the committee as a whole. A
preference was made by e-mail ballot, and the names of two nominees have
been presented to S. Beckwith and D. Leckrone for final selection.
- Dates for next meeting of the STUC have not been scheduled,
pending the selection of a new chair.
- The STUC entered executive session, and adjourned at 3:00 PM.
DISCLAIMER: All technical details reported above are
accurate as of 10 November 1998. For more details of items marked with
*, see the Space Telescope
Science Institute Newsletter, Volume 15, Number 4 (October 1998).
Readers should refer to the
STScI web site for updated
information.
Items preceeded with
§ are commented on in the
Report of the STUC.
This report submitted by
Frederick M. Walter
Chair, Space Telescope Users Committee
December 1998
fwalter@astro.sunysb.edu