JWST History: 2003-2004
Working on the Detailed Design
As a result of selecting all major partners in 2002, the JWST project began a re-plan phase
in order to bring the telescope design, the instrument designs and the science requirements
in concord and to make the whole project fit within the previous estimated budget constraints.
A number of launch vehicle possibilities existed. ESA was willing to provide an Ariane 5 launch
vehicle that would allow simplifications in the primary mirror design. The effective area of the
primary mirror was reduced to 25 square meters (down from the 29.4 in the original TRW proposal.
TRW had been merged with Northrop Grumman and had become Northrop Grumman Space Technology, NGST!).
The number of segments were reduced from 36 to 18. The originally combined NIRCam and guider were
split into two separate instruments, with the US providing the NIRCam and CSA providing the guider.
The MIRI cryocooler was replaced by a cryostat to eliminate the need for an additional technology
development (this decision was reversed in 2005).
In the summer of 2003, the NIRCam and NIRSpec teams chose HgCdTe (Rockwell)
technology for their NIR detectors. Similarly NASA selected the beryllium-based
mirror technology for the telescope's 6.5-meter primary mirror based upon the
recommendation of the JWST prime contractor, Northrop Grumman. The technology had
been supplied by Ball Aerospace & Technologies Corporation. The production of the
beryllium-based mirrors began within a year (Press release).
The Project officially moved from Phase A (preliminary design studies) to Phase B.
In Phase B (which was ultimately a four year period, the detailed JWST design would
be developed. However, procurements started for some long lead items like the mirror segments.
In 2003, the STScI developed the Mission Operations Concept and was the primary author
on the individual science instruments operations concept documents.
With the ESA selection of AEDS/Astrium to develop the NIRSPec in July 2004,
the Project could initiate the initial development of system and subsystem
requirements within the context of specific (yet flexible) design. To aid this
process, the Science Working Group developed the Science Requirements Document (SRD).
The SRD is a detailed description of major science goals for the mission and the implied
performance requirements for the observatory and instruments. The latter are incorporated
in the Mission Requirements Document (MRD). With these documents and those at the element
level (observatory, ISIM, launch, and ground system), the Project passed the mission
System Requirements Review (SRR) in December 2003.
In 2004, as the JWST costs and NASA budgets became more mature and initial contracts
reviewed, all teams had to adjust their plans and budgets for a new Launch date of
August 2011. During the more detailed design and analysis phase in 2004, several
technical issues emerged. An example was the potential need to manage the JWST science
program in order to minimize the accumulation of angular momentum due to radiation
torques on the large sunshield. This issue would finally be resolved in 2007.
In 2004, Brush-Wellman delivered the first Be segment blanks to Axsys for machining and lightweighting.
In 2004, as a result of the Columbia accident, NASA grounded the shuttle system and halted
plans for a routine shuttle mission to repair the Hubble.
|