Visit Status Report for HST 18127

Sun May 03 05:09:29 EDT 2026
Visit Status Target(s) Configs Orbits Plan Windows
01 Implementation PA30-NE-A
WFC3/IR
1 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
02 Implementation PA30-NE-B
WFC3/IR
1 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
03 Implementation PA30-NE-A
WFC3/IR
2 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
04 Implementation PA30-NW-A
WFC3/IR
1 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
05 Implementation PA30-NW-B
WFC3/IR
1 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
06 Implementation PA30-NW-A
WFC3/IR
2 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
07 Implementation PA30-SE-A
WFC3/IR
1 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
08 Implementation PA30-SE-B
WFC3/IR
1 Aug 11, 2026 - Aug 22, 2026 (2026.223 - 2026.234)
09 Implementation PA30-SE-A
WFC3/IR
2 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)
10 Implementation PA30-SW-A
WFC3/IR
1 Aug 11, 2026 - Aug 22, 2026 (2026.223 - 2026.234)
11 Implementation PA30-SW-B
WFC3/IR
1 Aug 11, 2026 - Aug 22, 2026 (2026.223 - 2026.234)
12 Implementation PA30-SW-A
WFC3/IR
2 Aug 11, 2026 - Aug 17, 2026 (2026.223 - 2026.229)