| Visit | Status | Target(s) | Configs | Orbits | Plan Windows |
|---|---|---|---|---|---|
| 01 | Implementation | L08A0 L08A11 |
COS/NUV COS/FUV |
2 | Ready for long range planning, plan window not yet assigned |
| 02 | Implementation | L08A0 L08A9 L08A8 |
COS/NUV COS/FUV |
2 | Ready for long range planning, plan window not yet assigned |
| 03 | Implementation | L08A0 L08A7 |
COS/NUV COS/FUV |
3 | Ready for long range planning, plan window not yet assigned |
| 04 | Implementation | L08A0 L08A10 |
COS/NUV COS/FUV |
3 | Ready for long range planning, plan window not yet assigned |
| 05 | Implementation | L08A0 L08A3 |
COS/NUV COS/FUV |
3 | Ready for long range planning, plan window not yet assigned |
| 07 | Implementation | L08A0 L08A4 |
COS/NUV COS/FUV |
2 | Ready for long range planning, plan window not yet assigned |
| 08 | Implementation | L08A0 L08A1 |
COS/NUV COS/FUV |
2 | Ready for long range planning, plan window not yet assigned |
| 09 | Implementation | L08A0 L08A2 L08A5 |
COS/NUV COS/FUV |
3 | Ready for long range planning, plan window not yet assigned |
| 10 | Implementation | L08A0 L08A6 |
COS/NUV COS/FUV |
3 | Ready for long range planning, plan window not yet assigned |
| 11 | Implementation | L08A0 L08A2 L08A6 |
COS/NUV COS/FUV |
3 | Ready for long range planning, plan window not yet assigned |
| 12 | Implementation | L08A0 L08A2 |
COS/NUV COS/FUV |
3 | Ready for long range planning, plan window not yet assigned |