Visit Status Report for HST 18436

Sat Oct 17 06:57:52 EDT 2026
Visit Status Target(s) Configs Orbits Plan Windows
01 Implementation KOINTREAU-1
WFC3/UVIS
2 Dec 2, 2027 - Dec 3, 2027 (2027.336 - 2027.337)
02 Implementation KOINTREAU-1
WFC3/UVIS
2 Ready for long range planning, plan window not yet assigned
03 Implementation KOINTREAU-4
WFC3/UVIS
2 Ready for long range planning, plan window not yet assigned
04 Implementation YSES-1
WFC3/UVIS
2 Jun 9, 2028 - Jun 18, 2028 (2028.161 - 2028.170)
05 Implementation ROXS-42B
WFC3/UVIS
2 Ready for long range planning, plan window not yet assigned
06 Implementation ROXS-42B
WFC3/UVIS
2 Apr 24, 2028 - May 8, 2028 (2028.115 - 2028.129)