Time Allocation Change History for 1503

Date Change Type Time Delta (hours) Reason
Jan 27, 2023 INSTRUMENT_PROBLEM 1.6 The AMB wants additional internal flats to check that NIRISS is working following the recovery.
Jan 11, 2023 ADMINISTRATION -9.2 These are executing as parallels, not internals.
Jan 11, 2023 ADMINISTRATION 9.2 These are executing as parallels, not internals.
Jan 23, 2020 OVERHEAD_CHANGE 0.5 APT 2020.1.1
Oct 16, 2019 ADMINISTRATION -9.2 This time allocation should be internal - not external.
Oct 16, 2019 ADMINISTRATION 9.2 This time allocation should be internal - not external.